The week of June 17th:
Parking Lot 6 (large parking lot in the back of campus) will be closed for paving repairs. Weather dependent this work will take approximately 1 week.
Roofers will be here to replace the rubber roofs on St. Joe’s and Cosgrave. This work will take approximately 2 – 2 1/2 weeks. The work at St. Joe’s will start the week of June 17th and there will be little to no access to parking or deliveries behind the Administration Building.
Cosgrave roof work will start when St. Joe’s is finished.
Painting is still occurring in the Administration Building in the stairwells and on the second floor.
The Library Renovation and St. Gert’s residence rooms and Health Services are all underway and on schedule.
An announcement will be forthcoming when the new floor will be installed on the second floor of the Administration Building.
Thank you in advance for your patience as these projects are being completed and you may need to detour to get to certain parts of campus.